Project Name Anchored Pile Walling Project Specification piling wall 1 km around huge lake area 60 rai TPC’s anchoring system Contract Amount 50 million THB
![AMTEC](https://www.tpcconcrete.com/wp-content/uploads/2021/06/AMTEC-300x169.jpg)
AMTEC
Project Name AMTEC Project Specification various size of PC beams customized design of PC beams Contract Amount 8.00 million THB Project Duration 6 Months Location
![Solaria Hotel](https://www.tpcconcrete.com/wp-content/uploads/2021/06/70551-300x169.jpg)
Solaria Hotel
Project Name Solaria Hotel Project Specification long span PC beam high QA/QC supported Contract Amount 3.00 million THB Project Duration 3 Months Location Asoke, Bangkok,
![Hino Suvarnabhumi](https://www.tpcconcrete.com/wp-content/uploads/2021/06/001-300x142.png)
Hino Suvarnabhumi
Project Name Hino Suvarnabhumi Project Specification PC column PC beam PC wall precast mock-up pilot project of Thai Obayashi Contract Amount 4.00 million THB Project
![Nestle Navanakorn](https://www.tpcconcrete.com/wp-content/uploads/2021/06/009-1-300x146.jpg)
Nestle Navanakorn
Project Name Nestle Navanakorn Project Specification PC column PC beam tight schedule speedy construction Contract Amount 5.00 million THB Project Duration 4 Months Location Navanakorn,
![PIC Factory](https://www.tpcconcrete.com/wp-content/uploads/2021/06/PIC-Factory-300x225.jpg)
PIC Factory
Project Name PIC Factory Project Specification Total precast solution Precast retaining wall PC column PC beam Hollow core slab Contract Amount 40 million THB Project
![Lat Pho Retaining Platform](https://www.tpcconcrete.com/wp-content/uploads/2021/06/473606-300x225.jpg)
Lat Pho Retaining Platform
Project Name Lat Pho Retaining Platform Project Specification Spun piles PC slab Steel pipe (High Grate Imported China) driving Project Duration 4 Months Location Samut
![ACT Apartment](https://www.tpcconcrete.com/wp-content/uploads/2021/06/286294-300x169.jpg)
ACT Apartment
Project Name ACT Apartment Project Specification Total precast solution 4 Floors + roof slab Speedy construction with all precast members Contract Amount 15 million THB